Working backwards from a launch date

7 min readLaunching and growingUpdated

Build a launch calendar from the on-sale date, with dated approvals, confirmed material and making times, and spare time beside the steps that can delay delivery.

Quick answers from this guide

Where should a clothing brand's launch calendar start?

Start with the date the clothes have to be on sale, then establish when they must arrive at the place that will hold the stock. Work backwards through transport, release from the maker, final checks, making and material delivery. Date the approvals needed before those steps can begin, then check the sequence against actual material availability and the maker's working calendar.

How far ahead should work on the clothes begin?

Work backwards from the date the clothes must be ready to sell. Ask the maker for material availability, sampling and production dates, then include transport, receiving and launch preparation. Newly developed fabric adds work that stock fabric may avoid. Use confirmed dates and explicit allowances for revisions; there is no single lead time for every first collection.

Where should spare time sit in the launch calendar?

Keep spare time beside the steps whose delay would move delivery: material decisions, fabric arrival and final approval before cutting. Leave room before the final check for repairs or another check, and between release and transport handover for documents and collection. Record how much of that reserve remains whenever it is used; the original allowance no longer describes the available time.

How should sample approvals appear in the calendar?

Give sending a sample and approving it separate dates. Record when the sample is due, when it was sent, who must respond and the response deadline. Record the decision as well as the response date. Comments asking for another sample leave work waiting, so allow for another review and identify the approval that permits the maker to begin cutting.

What should change when a date is missed?

Record the missed date and identify the next step it affects immediately. Check whether approved clothes or colours can be made first, whether an available material can meet the agreed requirements, or whether part of the order can arrive separately. Confirm the consequences for cost and transport before changing bookings. If recovery cannot preserve the agreed clothes and quality, revise the delivery commitment.

On this page 7 sections

Build the launch calendar backwards from the date the clothes have to be on sale, and keep spare time beside the decisions and deliveries that could move that date. Establish when the stock must arrive, then work back to when it must leave the maker. Making time is only one part of the plan. Fabric preparation and the decisions that release each stage also need dates.

Illustration of a planning table connecting garment development, online store preparation and delivery work.
Studio illustrationProduct development, the storefront and delivery need a connected plan. Set dates around dependencies and confirmed commitments; this illustration does not prescribe a launch timetable.

01The on-sale date needs an arrival date beneath it

Write down the on-sale date and the required arrival date separately. Then agree the transport plan that connects arrival to the day the clothes leave the maker. A date for leaving the maker cannot stand in for a date when stock will be available for sale. Keep both visible so a change to transport shows up in the launch plan.

Working backwards from departure, allow for the final check of the clothes, packing and shipping documents. Include the brand's permission to send the order if that is part of the agreement. Booking a check and passing it are separate events. The calendar needs to show when the result will be available and who can authorise the next step.

Place the making period before those final steps. Before making begins, the fabric and other parts must be available, and the sample production will be checked against must be approved. Continue backwards until the calendar reaches the decisions about what is being made and the order confirmation. Each date should describe something that permits the next piece of work to begin.

02The fabric route determines how early work starts

There is no single starting date for every clothing launch. A newly developed fabric needs design, production and approval work that fabric available from stock may avoid. Ask for dates against the actual material route, sample reviews and production availability. Add transport and receiving time before deciding when the clothes can be offered for sale.

The difference begins with what already exists. Fabric being developed needs its own preparation and approvals before it can be made in the quantity required. Fabric available from stock still needs confirmation that the required quantity and colour are available, followed by delivery. A calendar that gives both routes the same allowance hides work in the first and assumptions in the second.

Ask what has to happen before usable fabric reaches the maker. Put those steps into the calendar separately. Approval of a colour may have to happen before the main quantity of fabric can be dyed. Printing may need an approved test on fabric. A wash or finish may also need an agreed reference before work proceeds.

Clothes that share fabric need a shared plan for it. Record the total requirement across those designs before booking the fabric. The minimum a fabric maker will run can affect whether to share cloth across designs or use an available alternative. Settle that choice before the booking deadline arrives.

03Approval dates must include time to respond and try again

A sample arriving does not complete an approval. It starts the review. Give the maker's submission and the brand's response separate dates, and name the person who will decide. Record when each happened alongside the original plan. That makes a late response as visible as a late sample.

Leave room for another attempt where one may be needed. The first colour test may be rejected. A sample used to check how the clothes fit may need changes before the next sample can be made. Scheduling the first submission as the final approval removes the time needed to respond to what arrives.

Keep comments about a sample together in one document. State whether the work is approved to continue or another sample is required. Comments alone can leave that decision unclear. For a print, retain the approved file version and date, with its size and position settled before permission to print the order is given.

Distinguish a sample used to develop the fit from the final sample production is checked against. The latter needs an approval date before cutting. Allow time for final comments at that point, too. A calendar that reaches cutting with an unresolved sample has reached a decision still waiting to be made.

04Spare time belongs beside the steps that threaten delivery

Find the chain of work where a delay would move the departure date unless something changes. Cutting waiting for fabric is one such connection. Put spare time beside these steps instead of adding the same allowance to every task. Work that can move without affecting delivery already has some room.

Keep an allowance before material commitments or permission to start making, so another comment round can happen. Set a response deadline that leaves this room intact. Waiting until the last possible decision date to follow up spends the allowance before anyone has decided how to use it.

Leave space between fabric arrival and cutting for checking the colour or deciding whether material needs replacing. Keep that time available until the fabric has been checked. Before the final inspection, reserve room for minor repairs, packing completion or another check. Between release and the agreed transport handover, allow for documents and collection arrangements.

Treat these allowances as reserves with a remaining balance of time. When a delay uses some of the reserve, change the calendar to show what is left. A launch date may still hold while the room to recover has disappeared. Both facts belong in the update; showing the unchanged end date alone conceals the next risk.

05Check available weeks before accepting the backwards plan

Once the dates are placed, read the plan forwards with the maker. Confirm that each decision can happen in time to release the work after it. If the latest workable order confirmation date has already passed, change the plan. Material choice or the delivery arrangement may need to change before the dates can be credible.

Check the maker's working calendar and the calendars behind the materials. Factory holidays remove working time. Busy periods can leave a week technically available while other orders compete for it. Ask which weeks are unavailable and which still need a booking, then mark those distinctions on the launch calendar.

Transport needs the same attention. Busy shipping periods can make space harder to secure and journey times less predictable. The plan may need an earlier departure from the maker. Do not leave that decision until the clothes are packed.

Some work can run alongside fabric preparation. Care-label artwork and packaging details can progress where they do not rely on an unresolved fabric or sample decision. Check that connection before committing to anything that would need remaking after a change. Doing work at the same time helps only when the decisions supporting it are ready.

06Several launch dates still share one material plan

If the clothes go on sale in separate releases, give each release its own delivery date and sample review. Also set the date after which its designs are fixed for making. Fabric shared across releases still needs one plan covering the full quantity required. Separate launch dates do not create separate supplies of the same cloth.

A design added later may use fabric already allocated to an earlier release, or require another fabric booking. Update the total fabric requirement whenever the designs are fixed. Check this before accepting an addition to the launch, while the effect on other clothes can still be understood and agreed.

Book making time for each release as part of the overall plan. A later launch needs a confirmed place in the maker's calendar, even when its fabric has already been arranged.

A repeat order also needs materials and making time. An approved design can remove much of the development work, but the fabric and an available production week still have to exist. If repeats form part of the plan, discuss a fabric reserve and a possible making window early, then confirm or release them when the decision to reorder is made.

07A missed date needs a decision while options remain

Update the calendar as soon as a step is completed, missed or changed. Identify the next affected step and follow the connection through to departure and arrival. A late colour approval can move dyeing, fabric delivery and cutting. A regular review helps keep the plan current, but a delay that threatens delivery needs attention before the next scheduled conversation.

Start by checking whether approved designs or colours can proceed while another waits. An available material may offer another route if it meets the agreed requirements and receives approval. Record any cost effect and the new date that work can begin. Keep changes to the clothes visible alongside changes to time.

Sending part of the order separately can protect an initial delivery when the ready quantity supports the launch plan. It also creates more packing lists, invoices and transport instructions. Bring the people arranging transport and documents into that decision. Faster transport needs a cost discussion before booking; it cannot replace unfinished approvals or making.

If the remaining time cannot protect the agreed clothes and quality, revise the delivery commitment and name who will communicate it. Keep the previous calendar, date the replacement and record why it changed. Show actual dates beside planned dates and the spare time still available. That gives the next decision a basis in the work completed and the work still waiting.

Working on a range

Get help turning the next decision into a practical plan.

Talk about your idea

Choosing which market to launch in first

The launch date is a design constraint

A discount is a design decision

Against launching with everything